For the “Wake Up Big Canoe” group and their question under Sconti complex - Did this get out of hand or what?

——————————————–

From the article, “Big Canoe should hire amenities manager, Roger Klask says,” by Ann Dickerson, Smoke Signals, November 2007, Page 3A.

“Crouch asked board members to approve a document he wrote in response to questions by some of the Finance/Audit Committee members.” [A document on his historical view of how the Sconti Restaurant rebuild played out.]

One Director wouldn’t approve Mr. Crouch’s document.

“The board did not take a vote on the document presented by Crouch.”

——————————————–

Of special interest from Mr. Bob Crouch’s historical view document regarding the new Sconti clubhouse:

“Questions have been raised from sources with no construction or project management experience regarding claims that the clubhouse project is on [over] budget. They question a volunteer committee with vast experience. Simply stated, when the scope of a project changes the budget changes. The manager of that project then works to deliver it on the revised budget. Missing the budget means that, given the same scope, costs have gotten out of line. To date this has not occurred due to the Herculean efforts of the Building Committee.”

——————————————–

Let’s read the following again, “Questions have been raised from sources with no construction or project management experience.”

The following is a response from one of those so-called inexperienced sources:

===============================

A property owner’s and retired certified project manager’s analysis of the POA Board President’s historical view (document) of how the Sconti Restaurant rebuild played out:

Overall Mr. Crouch’s historical view regarding the new Sconti clubhouse sounds good…to the untrained non-project management eye.

As a project manager I was responsible for bringing in or completing projects in scope, on time, and on budget.

It is obvious that the key factor for this project was time with all else left to the wind. As a long time certified project manager, this project would be a prime example of how not to do a project.

Justifying changes in a budget by project scope changes [change orders] and still denying a bid process in the interest of time may save time but will accelerate cost.

The continual floating scope-changes [change orders] basically indicate that there was no well defined or planned project to begin with. Therefore, the continual changes in project content and objective cause what is known as scope creep. Without a firm project plan or firm project requirements a timeline scope creep changes must be accepted or the project will fall short of expectations.

Scope creep is a well-known cause of budget creep [budget increases] which puts the Sconti project in the position it is in today.

While scope creep can occur on any project it is usually managed to limit impact. The Sconti project appears to be defined and based on little other than scope creep [change orders]. This project appears to be an almost totally seat-of-pants operation. What project management there is appears to be after the fact project management.

If you ignore the basic practices and principles contained in the Project Management Institute’s, PMBOK (Project Management Body of Knowledge), there is no way, other than pure luck, that this or any project can be completed in an cost effective manner.

Change Order managed development is probably the most cost-escalating method of performing a project. To justify the Sconti cost because there have been so many scope changes is to say, “We did a project incorrectly from day one.” It was poorly initiated, improperly planned, and improperly executed from day one or there would not have been so many, many scope changes [change orders]. If I were to grade it, I would give it a “D” taking into account some well-intention, well-meaning individuals. The truth is that in my heart I know had I done a project in this manner, I would have been fired…period!

[Here the writer does into the elements of successful PMBOK project management and grades the Sconti project on each of the elements. Not published due to length.]

The Sconti Project failed to follow many of the project process areas either completely or even in part. The Sconti project was treated more like a rush order or rush to judgment.

Because communications were improperly (not done) in the beginning (no communication plan or one that was not properly thought through), complete customer and property owner reaction and feedback were overlooked which caused the project requirements and scope to be ill defined. This caused major revisions to be made mid-stream and ultimately perpetuated almost constant revision.

The Sconti Committee cannot be blamed for this project’s failures. The project was doomed from the start to have accelerating costs. The added costs can only be blamed on misguided decisions of the current and past Board Presidents.

Mr. Crouch’s history, whether he realizes it or not, bears this out. There have been so many project management mistakes made that the Sconti Project could be used in training as to how not to do a project.

Regrettably, the committee is full of knowledgeable people who are well intended, but if unbalanced pressure is brought to bear, that forced them to go outside established processes and procedures, then there is no way that they could have been successful in managing cost.

In the case of the Sconti, poor Board leadership, pressure to rush, pressure to not involve the community up front, and pressure to get it done too quickly doomed this project from the start to rampant cost escalation. All of the experience in the world could not stop the avalanche once it was started.

When a project is mis-directed by upper management, no project manager can complete a project in scope, on time, and within budget. Bragging about your past successes and purported skills is not a guarantee of another successful project.

Proper planning, requirements collection for scope development, proper budgeting bolstered with proper bidding and contracting principles and frankly following all of the standard project management processes was how this project should have been approached.

Most, if not all principles of successful project management were thrown out the window for the sake of ego and bragging. In other words, substance was replaced by ego.

The Sconti Project, as it was handled, was a Trojan horse from day one. The POA property owners were sold a bad bill of goods and are having their wallets emptied by some individuals who say that they are doing a good job. Ask any of the Sconti Committee members with project management experience if they have been permitted to do build a fiscally responsible Sconti restaurant. If they are open and honest with you, they will say no.

It is said the board of directors could not stop this fiasco…probably because of restrictions place on them, lack of project management understanding, and lack of overall experience, they didn’t recognized the pending financial disaster.

The Sconti may wind up being a beautiful facility but the cost will be very dear. I am guessing the project will [be] in the neighborhood of five to seven million dollars more than it should have cost in the name of getting it done in a hurry.

The annual operating losses experienced in years past will seem like pocket change in comparison to this costly overrun along with the annual losses likely to be generated going forward.

The Sconti Project is Big Canoe’s equivalent to the government’s $600 dollar toilet seats and the $223 million dollar Alaskan bridge to nowhere (recently cancelled).

It is too bad we could not rally enough public outrage in this community early-on to stop this. Now we will all pay dearly and continue to pay as long as we live in Big Canoe.

Apathy has cost us millions and now we have to find a way to live with it.

I for one am outraged!